单项选择题A.软件元素 B.软件项目C.软件配置项D.软件过程
单项选择题A.机房 B.管理间C.设备间 D.配线间
单项选择题Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is () .
A.16 days B.14 days C.19 days D.20 days
单项选择题Which of the following is not part of a modern quality management concept ( )
单项选择题Which of the following is not part of the quality assurance process ( )