单项选择题Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is () .
A.16 days B.14 days C.19 days D.20 days
单项选择题Which of the following is not part of a modern quality management concept ( )
单项选择题Which of the following is not part of the quality assurance process ( )
单项选择题The ( ) has several major components, including the system kernel, a memory management system, the file system manager, device drivers, and the system libraries.
单项选择题Which of the following elements can be called the key element of a computer ( )