单项选择题

A.Planned valueB.Earned valueC.Actual costD.Cost varian……

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

A.Planned value
B.Earned value
C.Actual cost
D.Cost variance