A.Probability-Impact matrix B.Pareto chart C.R-Chart D.PERT (Program Evaluation and Review Technique) analysis
单项选择题WhichistheMOSTeffectivemethodforgeneratingsupportforyourprojectplan?()
A.Requiring stakeholders to sign-off on project plan components B.Requesting input from all stakeholders during the planning process C.Providing an open line of communication regarding the project D.Clearly illustrating how the project relates to the company’s objectives
单项选择题Whichfactorhasthegreatestimpactontheestimatedperunitlaborcostforaproject?()
A.Historical information B.Use of outside vendors C.Change control processes D.Human resource skill level requirements
单项选择题TheprojectsponsorwantstheprojectmanagertodevelopandimplementQualityManagementtechniquestoensureasmoothprojecttransitiontothedeploymentphase.WhatisanappropriateQualityManagementtechniquetoimplement?()
A.Evaluate phase exit milestones using sufficiency criteria B.Flexible entry and exit criteria to minimize schedule delays C.Quality measures reported only to the project steering committee D.Many work teams with few members to maximize the number of deliverable hand-offs
单项选择题Iftheorganizationalspendingplanhasallocated$100,000foraproject,andthehighlevelbudgetestimateforthatprojectis$200,000;whichofthefollowingisaccurate?()
A.The high level budget estimates are inaccurate B.The organizational spending plan is inaccurate C.The budget is not aligned with the spending plan of the organization D.The detailed bottom up budget will need to be adjusted
单项选择题Whatistheroleofthelinemanagerinaprojectplan?()
A.Provide resources to a project B.Request requirements changes C.Resolve team conflicts D.Control the project budget