An administrator is interested in implementing multiple shared processor pools on a new Power 595. How many user-customizable multiple shared processor pools are available?()
A. 63 B. 64 C. 254 D. 255
单项选择题On a Hardware Management Console (HMC) at version 7, an administrator has an LPAR defined with a minimum of 0.1 processors and a maximum of 4 processors. The administrator wants to go from 1 processing unit to 3 processing units for this partition. In order to make the change, what value should the administrator enter into the add processor resources window? ()
A. 2 B. 3 C. 1.0 D. 2.9
单项选择题A customer has a key application running in a logical partition on a POWER5 system. The customer wants the ability to run the application with minimal down time using Live Partition Mobility. Which of the following is the minimum PowerVM edition and hardware configuration that will support the customer requirement?()
A. PowerVM Standard Edition on POWER6 hardware B. PowerVM Standard Edition with POWER5 hardware C. PowerVM Enterprise Edition with POWER6 hardware D. PowerVM Enterprise Edition with POWER5 hardware
单项选择题A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()
A. vmstat and iostat data from the older machines B. The number of CPUs that were installed in the original machines C. Data from Workload Estimator (WLE) and IBM Performance Management (PM) D. Performance data that is collected from the new system after it has been put into production
单项选择题AnadministratorhasarequirementtomirrortheoperatingsystemonaVIOserver.WhichofthefollowingIOScommandswillachievethis?()
A. mirrorvg B. iosmirror C. mirrorios D. mkiosmirror
单项选择题A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system. How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()
A. Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server. B. Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system. C. Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR. D. Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.