In the process of communication requirement analysis, t……

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication. According to Metcalfe’s Law, a project with 10 stakeholders has () potential communication channels.

A、10
B、45
C、50
D、100